ACME Solar Starts Commercial Operations of 57.69 MW Renewable Project
By Tick2Trade
1 min read

ACME Solar Starts Commercial Operations of 57.69 MW Renewable Project

ACME Solar commissions 57.69 MW FDRE project in Rajasthan, starting commercial operations on November 21, 2026.

ACME Solar Commissioning Details

ACME Solar Holdings Limited, through its subsidiary ACME Sigma Urja Private Limited, has commissioned a firm and dispatchable renewable energy (FDRE) project with a contracted capacity of 57.69 MW. This includes a solar capacity of 100.02 MW combined with a battery energy storage system (BESS) capacity of 57.69 MW / 265.38 MWh.

Project Location and Connection

The project is located at Village Kharnai, Tehsil Rawatbhata, District Chittorgarh, Rajasthan. It is connected to the Neemuch Pooling Station.

Commercial Operation Date and Agreement

The commercial operation date (COD) for this project is set for November 21, 2026. ACME Solar has signed a power purchase agreement (PPA) with NHPC Limited for this project.

This commissioning enhances ACME Solar's renewable energy capacity and supports its ongoing agreements in the sector.